[Code of Federal Regulations]
[Title 26, Volume 2]
[Revised as of April 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 26CFR1.141-7]

[Page 649-657]
 
                       TITLE 26--INTERNAL REVENUE
 
    CHAPTER I--INTERNAL REVENUE SERVICE, DEPARTMENT OF THE TREASURY 
                               (CONTINUED)
 
PART 1_INCOME TAXES--Table of Contents
 
Sec. 1.141-7  Special rules for output facilities.

    (a) Overview. This section provides special rules to determine 
whether arrangements for the purchase of output from an output facility 
cause an issue of bonds to meet the private business tests. For this 
purpose, unless otherwise stated, water facilities are treated as output 
facilities. Sections 1.141-3 and 1.141-4 generally apply to determine 
whether other types of arrangements for use of an output facility

[[Page 650]]

cause an issue to meet the private business tests.
    (b) Definitions. For purposes of this section and Sec. 1.141-8, the 
following definitions and rules apply:
    (1) Available output. The available output of a facility financed by 
an issue is determined by multiplying the number of units produced or to 
be produced by the facility in one year by the number of years in the 
measurement period of that facility for that issue.
    (i) Generating facilities. The number of units produced or to be 
produced by a generating facility in one year is determined by reference 
to its nameplate capacity or the equivalent (or where there is no 
nameplate capacity or the equivalent, its maximum capacity), which is 
not reduced for reserves, maintenance or other unutilized capacity.
    (ii) Transmission and other output facilities--(A) In general. For 
transmission, distribution, cogeneration, and other output facilities, 
available output must be measured in a reasonable manner to reflect 
capacity.
    (B) Electric transmission facilities. Measurement of the available 
output of all or a portion of electric transmission facilities may be 
determined in a manner consistent with the reporting rules and 
requirements for transmission networks promulgated by the Federal Energy 
Regulatory Commission (FERC). For example, for a transmission network, 
the use of aggregate load and load share ratios in a manner consistent 
with the requirements of the FERC may be reasonable. In addition, 
depending on the facts and circumstances, measurement of the available 
output of transmission facilities using thermal capacity or transfer 
capacity may be reasonable.
    (iii) Special rule for facilities with significant unutilized 
capacity. If an issuer reasonably expects on the issue date that persons 
that are treated as private business users will purchase more than 30 
percent of the actual output of the facility financed with the issue, 
the Commissioner may determine the number of units produced or to be 
produced by the facility in one year on a reasonable basis other than by 
reference to nameplate or other capacity, such as the average expected 
annual output of the facility. For example, the Commissioner may 
determine the available output of a financed peaking electric generating 
unit by reference to the reasonably expected annual output of that unit 
if the issuer reasonably expects, on the issue date of bonds that 
finance the unit, that an investor-owned utility will purchase more than 
30 percent of the actual output of the facility during the measurement 
period under a take or pay contract, even if the amount of output 
purchased is less than 10 percent of the available output determined by 
reference to nameplate capacity. The reasonably expected annual output 
of the generating facility must be consistent with the capacity reported 
for prudent reliability purposes.
    (iv) Special rule for facilities with a limited source of supply. If 
a limited source of supply constrains the output of an output facility, 
the number of units produced or to be produced by the facility must be 
determined by reasonably taking into account those constraints. For this 
purpose, a limited source of supply shall include a physical limitation 
(for example, flow of water), but not an economic limitation (for 
example, cost of coal or gas). For example, the available output of a 
hydroelectric unit must be determined by reference to the reasonably 
expected annual flow of water through the unit.
    (2) Measurement period. The measurement period of an output facility 
financed by an issue is determined under Sec. 1.141-3(g).
    (3) Sale at wholesale. A sale at wholesale means a sale of output to 
any person for resale.
    (4) Take contract and take or pay contract. A take contract is an 
output contract under which a purchaser agrees to pay for the output 
under the contract if the output facility is capable of providing the 
output. A take or pay contract is an output contract under which a 
purchaser agrees to pay for the output under the contract, whether or 
not the output facility is capable of providing the output.
    (5) Requirements contract. A requirements contract is an output 
contract, other than a take contract or a take or

[[Page 651]]

pay contract, under which a nongovernmental person agrees to purchase 
all or part of its output requirements.
    (6) Nonqualified amount. The nonqualified amount with respect to an 
issue is determined under section 141(b)(8).
    (c) Output contracts--(1) General rule. The purchase pursuant to a 
contract by a nongovernmental person of available output of an output 
facility (output contract) financed with proceeds of an issue is taken 
into account under the private business tests if the purchase has the 
effect of transferring the benefits of owning the facility and the 
burdens of paying the debt service on bonds used (directly or 
indirectly) to finance the facility (the benefits and burdens test). See 
paragraph (c)(4) of this section for the treatment of an output contract 
that is properly characterized as a lease for Federal income tax 
purposes. See paragraphs (d) and (e) of this section for rules regarding 
measuring the use of, and payments of debt service for, an output 
facility for determining whether the private business tests are met. See 
also Sec. 1.141-8 for rules for when an issue that finances an output 
facility (other than a water facility) meets the private business tests 
because the nonqualified amount of the issue exceeds $15 million.
    (2) Take contract or take or pay contract. The benefits and burdens 
test is met if a nongovernmental person agrees pursuant to a take 
contract or a take or pay contract to purchase available output of a 
facility.
    (3) Requirements contract--(i) In general. A requirements contract 
may satisfy the benefits and burdens test under paragraph (c)(3)(ii) or 
(iii) of this section. See Sec. 1.141-15(f)(2) for special effective 
dates for the application of this paragraph (c)(3) to issues financing 
facilities subject to requirements contracts.
    (ii) Requirements contract similar to take contract or take or pay 
contract. A requirements contract generally meets the benefits and 
burdens test to the extent that it contains contractual terms that 
obligate the purchaser to make payments that are not contingent on the 
output requirements of the purchaser or that obligate the purchaser to 
have output requirements. For example, a requirements contract with an 
industrial purchaser meets the benefits and burdens test if the 
purchaser enters into additional contractual obligations with the issuer 
or another governmental unit not to cease operations. A requirements 
contract does not meet the benefits and burdens test, however, by reason 
of a provision that requires the purchaser to pay reasonable and 
customary damages (including liquidated damages) in the event of a 
default, or a provision that permits the purchaser to pay a specified 
amount to terminate the contract while the purchaser has requirements, 
in each case if the amount of the payment is reasonably related to the 
purchaser's obligation to buy requirements that is discharged by the 
payment.
    (iii) Wholesale requirements contract--(A) In general. A 
requirements contract that is a sale at wholesale (a wholesale 
requirements contract) may satisfy the benefits and burdens test, 
depending on all the facts and circumstances.
    (B) Significant factors. Significant factors that tend to establish 
that a wholesale requirements contract meets the benefits and burdens 
test include, but are not limited to--
    (1) The term of the contract is substantial relative to the term of 
the issue or issues that finance the facility; and
    (2) The amount of output to be purchased under the contract 
represents a substantial portion of the available output of the 
facility.
    (C) Safe harbors. A wholesale requirements contract does not meet 
the benefits and burdens test if--
    (1) The term of the contract, including all renewal options, does 
not exceed the lesser of 5 years or 30 percent of the term of the issue; 
or
    (2) The amount of output to be purchased under the contract (and any 
other requirements contract with the same purchaser or a related party 
with respect to the facility) does not exceed 5 percent of the available 
output of the facility.
    (iv) Retail requirements contract. Except as otherwise provided in 
this paragraph (c)(3), a requirements contract that is not a sale at 
wholesale does not meet the benefits and burdens test.

[[Page 652]]

    (4) Output contract properly characterized as a lease. 
Notwithstanding any other provision of this section, an output contract 
that is properly characterized as a lease for Federal income tax 
purposes shall be tested under the rules contained in Sec. Sec. 1.141-3 
and 1.141-4 to determine whether it is taken into account under the 
private business tests.
    (d) Measurement of private business use. If an output contract 
results in private business use under this section, the amount of 
private business use generally is the amount of output purchased under 
the contract.
    (e) Measurement of private security or payment. The measurement of 
payments made or to be made by nongovernmental persons under output 
contracts as a percent of the debt service of an issue is determined 
under the rules provided in Sec. 1.141-4.
    (f) Exceptions for certain contracts--(1) Small purchases of output. 
An output contract for the use of a facility is not taken into account 
under the private business tests if the average annual payments to be 
made under the contract do not exceed 1 percent of the average annual 
debt service on all outstanding tax-exempt bonds issued to finance the 
facility, determined as of the effective date of the contract.
    (2) Swapping and pooling arrangements. An agreement that provides 
for swapping or pooling of output by one or more governmental persons 
and one or more nongovernmental persons does not result in private 
business use of the output facility owned by the governmental person to 
the extent that--
    (i) The swapped output is reasonably expected to be approximately 
equal in value (determined over periods of three years or less); and
    (ii) The purpose of the agreement is to enable each of the parties 
to satisfy different peak load demands, to accommodate temporary 
outages, to diversify supply, or to enhance reliability in accordance 
with prudent reliability standards.
    (3) Short-term output contracts. An output contract with a 
nongovernmental person is not taken into account under the private 
business tests if--
    (i) The term of the contract, including all renewal options, is not 
longer than 3 years;
    (ii) The contract either is a negotiated, arm's-length arrangement 
that provides for compensation at fair market value, or is based on 
generally applicable and uniformly applied rates; and
    (iii) The output facility is not financed for a principal purpose of 
providing that facility for use by that nongovernmental person.
    (4) Certain conduit parties disregarded. A nongovernmental person 
acting solely as a conduit for the exchange of output among 
governmentally owned and operated utilities is disregarded in 
determining whether the private business tests are met with respect to 
financed facilities owned by a governmental person.
    (g) Special rules for electric output facilities used to provide 
open access--(1) Operation of transmission facilities by nongovernmental 
persons--(i) In general. The operation of an electric transmission 
facility by a nongovernmental person may result in private business use 
of the facility under Sec. 1.141-3 and this section based on all the 
facts and circumstances. For example, a transmission facility is 
generally used for a private business use if a nongovernmental person 
enters into a contract to operate the facility and receives compensation 
based, in whole or in part, on a share of net profits from the operation 
of the facility.
    (ii) Certain use by independent transmission operators. A contract 
for the operation of an electric transmission facility by an independent 
entity, such as a regional transmission organization or an independent 
system operator (independent transmission operator), does not constitute 
private business use of the facility if--
    (A) The facility is owned by a governmental person;
    (B) The operation of the facility by the independent transmission 
operator is approved by the FERC under one or more provisions of the 
Federal Power Act (16 U.S.C. 791a through 825r) (or by a state authority 
under comparable provisions of state law);
    (C) No portion of the compensation of the independent transmission 
operator

[[Page 653]]

is based on a share of net profits from the operation of the facility; 
and
    (D) The independent transmission operator does not bear risk of loss 
of the facility.
    (2) Certain use by nongovernmental persons under output contracts--
(i) Transmission facilities. The use of an electric transmission 
facility by a nongovernmental person pursuant to an output contract does 
not constitute private business use of the facility if--
    (A) The facility is owned by a governmental person;
    (B) The facility is operated by an independent transmission operator 
in a manner that satisfies paragraph (g)(1)(ii) of this section; and
    (C) The facility is not financed for a principal purpose of 
providing that facility for use by that nongovernmental person.
    (ii) Distribution facilities. The use of an electric distribution 
facility by a nongovernmental person pursuant to an output contract does 
not constitute private business use of the facility if--
    (A) The facility is owned by a governmental person;
    (B) The facility is available for use on a nondiscriminatory, open 
access basis by buyers and sellers of electricity in accordance with 
rates that are generally applicable and uniformly applied within the 
meaning of Sec. 1.141-3(c)(2); and
    (C) The facility is not financed for a principal purpose of 
providing that facility for use by that nongovernmental person (other 
than a retail end-user).
    (3) Ancillary services. The use of an electric output facility to 
provide ancillary services required to be offered as part of an open 
access transmission tariff under rules promulgated by the FERC under the 
Federal Power Act (16 U.S.C. 791a through 825r) (or by a state 
regulatory authority under comparable provisions of state law) does not 
result in private business use.
    (4) Exceptions to deliberate action rules--(i) Mandated wheeling. 
Entering into a contract for the use of electric transmission or 
distribution facilities is not treated as a deliberate action under 
Sec. 1.141-2(d) if--
    (A) The contract is entered into in response to (or in anticipation 
of) an order by the United States under sections 211 and 212 of the 
Federal Power Act (16 U.S.C. 824j and 824k) (or a state regulatory 
authority under comparable provisions of state law); and
    (B) The terms of the contract are bona fide and arm's-length, and 
the consideration paid is consistent with the provisions of section 
212(a) of the Federal Power Act.
    (ii) Actions taken to implement non-discriminatory, open access. An 
action is not treated as a deliberate action under Sec. 1.141-2(d) if 
it is taken to implement the offering of non-discriminatory, open access 
tariffs for the use of electric transmission or distribution facilities 
in a manner consistent with rules promulgated by the FERC under sections 
205 and 206 of the Federal Power Act (16 U.S.C. 824d and 824e) (or 
comparable provisions of state law). This paragraph (g)(4)(ii) does not 
apply, however, to the sale, exchange, or other disposition (within the 
meaning of section 1001(a)) of transmission or distribution facilities 
to a nongovernmental person.
    (iii) Application of reasonable expectations test to certain current 
refunding bonds. An action taken or to be taken with respect to electric 
transmission or distribution facilities refinanced by an issue is not 
taken into account under the reasonable expectations test of Sec. 
1.141-2(d) if--
    (A) The action is described in paragraph (g)(4)(i) or (ii) of this 
section;
    (B) The bonds of the issue are current refunding bonds that refund 
bonds originally issued before February 23, 1998; and
    (C) The weighted average maturity of the refunding bonds is not 
greater than the remaining weighted average maturity of the prior bonds.
    (5) Additional transactions as permitted by the Commissioner. The 
Commissioner may, by published guidance, set forth additional 
circumstances in which the use of electric output facilities in a 
restructured electric industry does not constitute private business use.
    (h) Allocations of output facilities and systems--(1) Facts and 
circumstances analysis. Whether output sold under an output contract is 
allocated to a particular facility (for example, a generating unit), to 
the entire system of the seller of that output (net of any uses of

[[Page 654]]

that system output allocated to a particular facility), or to a portion 
of a facility is based on all the facts and circumstances. Significant 
factors to be considered in determining the allocation of an output 
contract to financed property are the following:
    (i) The extent to which it is physically possible to deliver output 
to or from a particular facility or system.
    (ii) The terms of a contract relating to the delivery of output 
(such as delivery limitations and options or obligations to deliver 
power from additional sources).
    (iii) Whether a contract is entered into as part of a common plan of 
financing for a facility.
    (iv) The method of pricing output under the contract, such as the 
use of market rates rather than rates designed to pay debt service of 
tax-exempt bonds used to finance a particular facility.
    (2) Illustrations. The following illustrate the factors set forth in 
paragraph (h)(1) of this section:
    (i) Physical possibility. Output from a generating unit that is fed 
directly into a low voltage distribution system of the owner of that 
unit and that cannot physically leave that distribution system generally 
must be allocated to those receiving electricity through that 
distribution system. Output may be allocated without regard to physical 
limitations, however, if exchange or similar agreements provide output 
to a purchaser where, but for the exchange agreements, it would not be 
possible for the seller to provide output to that purchaser.
    (ii) Contract terms relating to performance. A contract to provide a 
specified amount of electricity from a system, but only when at least 
that amount of electricity is being generated by a particular unit, is 
allocated to that unit. For example, a contract to buy 20 MW of system 
power with a right to take up to 40 percent of the actual output of a 
specific 50 MW facility whenever total system output is insufficient to 
meet all of the seller's obligations generally is allocated to the 
specific facility rather than to the system.
    (iii) Common plan of financing. A contract entered into as part of a 
common plan of financing for a facility generally is allocated to the 
facility if debt service for the issue of bonds is reasonably expected 
to be paid, directly or indirectly, from payments under the contract.
    (iv) Pricing method. Pricing based on the capital and generating 
costs of a particular turbine tends to indicate that output under the 
contract is properly allocated to that turbine.
    (3) Transmission and distribution contracts. Whether use under an 
output contract for transmission or distribution is allocated to a 
particular facility or to a transmission or distribution network is 
based on all the facts and circumstances, in a manner similar to 
paragraphs (h)(1) and (2) of this section. In general, the method used 
to determine payments under a contract is a more significant contract 
term for this purpose than nominal contract path. In general, if 
reasonable and consistently applied, the determination of use of 
transmission or distribution facilities under an output contract may be 
based on a method used by third parties, such as reliability councils.
    (4) Allocation of payments. Payments for output provided by an 
output facility financed with two or more sources of funding are 
generally allocated under the rules in Sec. 1.141-4(c).
    (i) Examples. The following examples illustrate the application of 
this section:

    Example 1. Joint ownership. Z, an investor-owned electric utility, 
and City H agree to construct an electric generating facility of a size 
sufficient to take advantage of the economies of scale. H will issue $50 
million of its 24-year bonds, and Z will use $100 million of its funds 
for construction of a facility they will jointly own as tenants in 
common. Each of the participants will share in the ownership, output, 
and operating expenses of the facility in proportion to its contribution 
to the cost of the facility, that is, one-third by H and two-thirds by 
Z. H's bonds will be secured by H's ownership interest in the facility 
and by revenues to be derived from its share of the annual output of the 
facility. H will need only 50 percent of its share of the annual output 
of the facility during the first 20 years of operations. It agrees to 
sell 10 percent of its share of the annual output to Z for a period of 
20 years pursuant to a contract under which Z agrees to take that power 
if available. The facility will begin operation, and Z will begin to 
receive power, 4 years after the H bonds are issued. The measurement 
period for the property financed by

[[Page 655]]

the issue is 20 years. H also will sell the remaining 40 percent of its 
share of the annual output to numerous other private utilities under 
contracts of three years or less that satisfy the exception under 
paragraph (f)(3) of this section. No other contracts will be executed 
obligating any person to purchase any specified amount of the power for 
any specified period of time. No person (other than Z) will make 
payments that will result in a transfer of the burdens of paying debt 
service on bonds used directly or indirectly to provide H's share of the 
facilities. The bonds are not private activity bonds, because H's one-
third interest in the facility is not treated as used by the other 
owners of the facility. Although 10 percent of H's share of the annual 
output of the facility will be used in the trade or business of Z, a 
nongovernmental person, under this section, that portion constitutes not 
more than 10 percent of the available output of H's ownership interest 
in the facility.
    Example 2. Wholesale requirements contract. (i) City J issues 20-
year bonds to acquire an electric generating facility having a 
reasonably expected economic life substantially greater than 20 years 
and a nameplate capacity of 100 MW. The available output of the facility 
under paragraph (b)(1) of this section is approximately 17,520,000 MWh 
(100 MW x 24 hours x 365 days x 20 years). On the issue date, J enters 
into a contract with T, an investor-owned utility, to provide T with all 
of its power requirements for a period of 10 years, commencing on the 
issue date. J reasonably expects that T will actually purchase an 
average of 30 MW over the 10-year period. The contract is taken into 
account under the private business tests pursuant to paragraph (c)(3) of 
this section because the term of the contract is substantial relative to 
the term of the issue and the amount of output to be purchased is a 
substantial portion of the available output.
    (ii) Under paragraph (d) of this section, the amount of reasonably 
expected private business use under this contract is approximately 15 
percent (30 MW x 24 hours x 365 days x 10 years, or 2,628,000 MWh) of 
the available output. Accordingly, the issue meets the private business 
use test. J reasonably expects that the amount to be paid for an average 
of 30 MW of power (less the operation and maintenance costs directly 
attributable to generating that 30 MW of power), will be more than 10 
percent of debt service on the issue on a present-value basis. 
Accordingly, the issue meets the private security or payment test 
because J reasonably expects that payment of more than 10 percent of the 
debt service will be indirectly derived from payments by T. The bonds 
are private activity bonds under paragraph (c) of this section. Further, 
if 15 percent of the sale proceeds of the issue is greater than $15 
million and the issue meets the private security or payment test with 
respect to the $15 million output limitation, the bonds are also private 
activity bonds under section 141(b)(4). See Sec. 1.141-8.
    Example 3. Retail contracts. (i) State Agency M, a political 
subdivision, issues bonds in 2003 to finance the construction of a 
generating facility that will be used to furnish electricity to M's 
retail customers. In 2007, M enters into a 10-year contract with 
industrial corporation I. Under the contract, M agrees to supply I with 
all of its power requirements during the contract term, and I agrees to 
pay for that power at a negotiated price as it is delivered. The 
contract does not require I to pay for any power except to the extent I 
has requirements. In addition, the contract requires I to pay reasonable 
and customary liquidated damages in the event of a default by I, and 
permits I to terminate the contract while it has requirements by paying 
M a specified amount that is a reasonable and customary amount for 
terminating the contract. Any damages or termination payment by I will 
be reasonably related to I's obligation to buy requirements that is 
discharged by the payment. Under paragraph (c)(3) of this section, the 
contract does not meet the benefits and burdens test. Thus, it is not 
taken into account under the private business tests.
    (ii) The facts are the same as in paragraph (i) of this Example 3, 
except that the contract requires I to make guaranteed minimum payments, 
regardless of I's requirements, in an amount such that the contract does 
not meet the exception for small purchases in paragraph (f)(1) of this 
section. Under paragraph (c)(3)(ii) of this section, the contract meets 
the benefits and burdens test because it obligates I to make payments 
that are not contingent on its output requirements. Thus, it is taken 
into account under the private business tests.
    Example 4. Allocation of existing contracts to new facilities. Power 
Authority K, a political subdivision created by the legislature in State 
X to own and operate certain power generating facilities, sells all of 
the power from its existing facilities to four private utility systems 
under contracts executed in 1999, under which the four systems are 
required to take or pay for specified portions of the total power output 
until the year 2029. Existing facilities supply all of the present needs 
of the four utility systems, but their future power requirements are 
expected to increase substantially beyond the capacity of K's current 
generating system. K issues 20-year bonds in 2004 to construct a large 
generating facility. As part of the financing plan for the bonds, a 
fifth private utility system contracts with K to take or pay for 15 
percent of the available output of the new facility. The balance of the 
output of the new facility will be available for sale as required, but 
initially it is not anticipated that there

[[Page 656]]

will be any need for that power. The revenues from the contract with the 
fifth private utility system will be sufficient to pay less than 10 
percent of the debt service on the bonds (determined on a present value 
basis). The balance, which will exceed 10 percent of the debt service on 
the bonds, will be paid from revenues derived from the contracts with 
the four systems initially from sale of power produced by the old 
facilities. The output contracts with all the private utilities are 
allocated to K's entire generating system. See paragraphs (h)(1) and (2) 
of this section. Thus, the bonds meet the private business use test 
because more than 10 percent of the proceeds will be used in the trade 
or business of a nongovernmental person. In addition, the bonds meet the 
private security or payment test because payment of more than 10 percent 
of the debt service, pursuant to underlying arrangements, will be 
derived from payments in respect of property used for a private business 
use.
    Example 5. Allocation to displaced resource. Municipal utility MU, a 
political subdivision, purchases all of the electricity required to meet 
the needs of its customers (1,000 MW) from B, an investor-owned utility 
that operates its own electric generating facilities, under a 50-year 
take or pay contract. MU does not anticipate that it will require 
additional electric resources, and any new resources would produce 
electricity at a higher cost to MU than its cost under its contract with 
B. Nevertheless, B encourages MU to construct a new generating plant 
sufficient to meet MU's requirements. MU issues obligations to construct 
facilities that will produce 1,000 MW of electricity. MU, B, and I, 
another investor-owned utility, enter into an agreement under which MU 
assigns to I its rights under MU's take or pay contract with B. Under 
this arrangement, I will pay MU, and MU will continue to pay B, for the 
1,000 MW. I's payments to MU will at least equal the amounts required to 
pay debt service on MU's bonds. In addition, under paragraph (h)(1)(iii) 
of this section, the contract among MU, B, and I is entered into as part 
of a common plan of financing of the MU facilities. Under all the facts 
and circumstances, MU's assignment to I of its rights under the original 
take or pay contract is allocable to MU's new facilities under paragraph 
(h) of this section. Because I is a nongovernmental person, MU's bonds 
are private activity bonds.
    Example 6. Operation of transmission facilities by regional 
transmission organization. (i) Public Power Agency D is a political 
subdivision that owns and operates electric generation, transmission and 
distribution facilities. In 2003, D transfers operating control of its 
transmission system to a regional transmission organization (RTO), a 
nongovernmental person, pursuant to an operating agreement that is 
approved by the FERC under sections 205 and 206 of the Federal Power 
Act. D retains ownership of its facilities. No portion of the RTO's 
compensation is based on a share of net profits from the operation of 
D's facilities, and the RTO does not bear any risk of loss of those 
facilities. Under paragraph (g)(1)(ii) of this section, the RTO's use of 
D's facilities does not constitute a private business use.
    (ii) Company A is located in D's service territory. In 2004, Power 
Supplier E, a nongovernmental person, enters into a 10-year contract 
with A to supply A's electricity requirements. The electricity supplied 
by E to A will be transmitted over D's transmission and distribution 
facilities. D's distribution facilities are available for use on a 
nondiscriminatory, open access basis by buyers and sellers of 
electricity in accordance with rates that are generally applicable and 
uniformly applied within the meaning of Sec. 1.141-3(c)(2). D's 
facilities are not financed for a principal purpose of providing the 
facilities for use by E. Under paragraph (g)(2) of this section, the 
contract between A and E does not result in private business use of D's 
facilities.
    Example 7. Certain actions not treated as deliberate actions. The 
facts are the same as in Example 6 of this paragraph (i), except that 
the RTO's compensation is based on a share of net profits from operating 
D's facilities. In addition, D had issued bonds in 1994 to finance 
improvements to its transmission system. At the time D transfers 
operating control of its transmission system to the RTO, D chooses to 
apply the private activity bond regulations of Sec. Sec. 1.141-1 
through 1.141-15 to the 1994 bonds. The operation of D's facilities by 
the RTO results in private business use under Sec. 1.141-3 and 
paragraph (g)(1)(i) of this section. Under the special exception in 
paragraph (g)(4)(ii) of this section, however, the transfer of control 
is not treated as a deliberate action. Accordingly, the transfer of 
control does not cause the 1994 bonds to meet the private activity bond 
tests.
    Example 8. Current refunding. The facts are the same as in Example 7 
of this paragraph (i), and in addition D issues bonds in 2004 to 
currently refund the 1994 bonds. The weighted average maturity of the 
2004 bonds is not greater than the remaining weighted average maturity 
of the 1994 bonds. D chooses to apply the private activity bond 
regulations of Sec. Sec. 1.141-1 through 1.141-15 to the refunding 
bonds. In general, reasonable expectations must be separately tested on 
the date that refunding bonds are issued under Sec. 1.141-2(d). Under 
the special exception in paragraph (g)(4)(iii) of this section, however, 
the transfer of the financed facilities to the RTO need not be taken 
into account in applying the

[[Page 657]]

reasonable expectations test to the refunding bonds.

[T.D. 9016, 67 FR 59759, Sept. 23, 2002; 67 FR 70845, Nov. 27, 2002]